Infrastructure Development in full swing.
The Main campus has on-going
projects with an aggregate total budgeted cost of P 3.4 M. Leading
the pack is the Phase 1 construction of the Food Technology Building
(2.55M) which was started last January following the giving of the
award to a local contractor. This two-story building will be constructed
in two phases and will soon be operational after the completion
of phase one some time in July 2006. Also, construction of the historical
marker (250T) was resumed in December 2005 which was temporarily
stopped due to unfavorable weather condition. The project is 75%
complete and targeted to be completed in March 2006. Two comfort
rooms (600T) have been constructed to complement the increase of
student enrolment.
For the year 2006, buildings to be constructed (C) in the main campus
and repaired (R) are the following: Ceramics Building (R), Dormitory
(R) , Extension Services Building (C), Supply Office (R), School
Canteen (R) and Management Building (R).
|